Instrumentation basics · 1.6

The instrument deliverables: index, datasheet, hook-up, loop diagram, I/O list

25 October 2026 · 10 min read · ISA 5.1, ISA 5.4, ISA 20, IEC 61987

In short

The P&ID says what instruments a plant needs. The instrument deliverables say exactly what to buy, where and how to install it, how to wire it and how to configure it. This article maps the main documents, what each holds, where its data comes from and who uses it.

Where this matters

How it works

The main deliverables

DeliverableWhat it holdsMain inputsMain users
Instrument index (list)One row per tag: type, service, line or equipment, P&ID, location, signal and system, and the status of every related documentP&IDsEveryone, as the master
Instrument datasheetsFull specification of each instrument: process conditions, range, materials, connections, electrical, hazardous area, accessoriesIndex, process data, line list, piping classesProcurement, vendors
CalculationsFlow element, control valve, thermowell and relief valve sizingProcess data, line dataDatasheets, vendors, reviewers
I/O listEvery signal into and out of the DCS, SIS and PLCs, with its type (AI, AO, DI, DO), range, units and systemIndex, control narrative, cause and effectControl system engineers
Hook-up drawingsTypical installation details: impulse lines, valves, fittings and supports, with a bill of materialsDatasheets, piping classesConstruction, material take-off
Instrument location plansWhere each instrument and junction box sits on the plotIndex, piping layoutsConstruction, cable routing
Cable and junction box schedulesEvery cable: from, to, type, cores, length, gland. Every junction box and its terminals.Index, I/O list, location plansElectrical construction
Loop diagramsEach loop from field device to control system: every terminal, cable, core and junction boxI/O list, cable schedules, vendor drawingsCommissioning, maintenance
Cause and effect chartsWhich inputs cause which trips and actionsProcess safety studies, the SRSSIS engineers, commissioning

The order they are made in

P&ID → index → process data + calculations → datasheets → I/O list → hook-ups + locations → cables + JBs → loop diagrams

Work overlaps in practice, but the dependency order holds. A loop diagram cannot be finished before its cable numbers exist, and cables cannot be scheduled before the I/O and the locations are known. Each step is issued at a revision (for example IFR, then IFA, then IFC), and a change upstream re-opens every document downstream.

What the standards and practice say

DeliverableCommon references
Tags and symbolsISA 5.1, IEC 62424
DatasheetsISA 20 specification forms; IEC 61987 property lists (the basis of IEC 62683 product data)
Loop diagramsISA 5.4
Binary logic and cause and effectISA 5.2, plus project formats
Safety requirements behind the tripsIEC 61511 safety requirements specification (SRS)
Hook-ups, cables and JBsCompany and project standards; IEC 60079-14 for hazardous-area installation

Most operators impose their own templates and numbering. The engineering contractor's job is to deliver a consistent set in the client's format.

Worked example: one drum, traced through the deliverables

Take the compressor suction drum from article 1.3 and count what it adds to each document.

TagDatasheetI/O (system, type)Hook-upCables
LIT-4101YesDCS AILevel, DP type1
LV-4101Yes (with sizing)DCS AOValve, positioner air1
LT-4102YesSIS AILevel, DP type1
PDIT-4103YesDCS AIDP, gas service1
TE/TT/TW-4105Yes (TW with calculation)DCS AIThermowell, head-mounted transmitter1
XV-4106 + XYYesSIS DOValve, actuator air1
ZSO / ZSC-4106On the XV datasheetSIS DI × 2None1 (shared multicore)
PSV-4104Yes (with sizing)NoneNone0

Totals for this drum: 7 datasheets (more if the TE, TT and TW get separate sheets), 3 sizing calculations (LV, TW, PSV), 8 I/O points (DCS: 3 AI and 1 AO; SIS: 1 AI, 1 DO and 2 DI), 5 hook-up types, 7 field cables and 5 loop diagrams (loops 4101, 4102, 4103, 4105 and 4106).

What this example shows

When it fails: the fixes in order

  1. Make the index the single source. Every other document should take its tag list, service and location from the index, not from its own copy.
  2. Track the revision of each document against the index. Know which documents are out of date after each P&ID change.
  3. Freeze the inputs in order. Process data before datasheets, I/O before cables, cables before loop diagrams.
  4. Cross-check before each issue. Tags, ranges, I/O types and cable numbers should match across documents.
  5. Carry changes through every document. Use a change log that lists each document affected.

Common mistakes

Checklist

Quick reference

Further reading

The drum example is illustrative, and real counts depend on the project's typicals and wiring philosophy. ISA and IEC are named for identification only.